Question: You have been identified as the project manager for constructing a large shopping mall in your city. Which of the following are not necessarily stakeholders

You have been identified as the project manager for constructing a large shopping mall in your city. Which of the following are not necessarily stakeholders in your project? A. The suppliers of the project B. The tenants of the shopping mall C. A senior project manager in your organization who just completed a similar project. D. The chief financial officer of your company who controls the project finances. A tool that provides a visual representation of human resource allocation to a project, number of working hours and availability on the project is a: A. Resource Histogram B. Staff release plan C. Resource Breakdown Structure (RBS) D. Organization Breakdown Structure (OBS)