Question: You have been told to use the critical path method using the zero - method rule with a tolerance limit of + - 1 0
You have been told to use the critical path method using the zeromethod rule with a tolerance limit of percent. Where would you document this?
A Work performance information
B Schedule management plan
Schedule baseline
D
Project schedule