Question: You have committed to migrating your software platform from a server based to a cloud based product and also update to the latest version of
You have committed to migrating your software platform from a server based to a cloud based product and also update to the latest version of the product. The total cost of the project is $45,000 and it is supposed to be completed in five months. After two months, you find you have paid $20,000. The software company only bills for work performed, but charges a minimum of $8,000 a month. What is the schedule performance index?
Use up to two decimal points.