Question: You have completed a cost / benefit analysis for prospective projects . You have a meeting with the project sponsor and portfolio manager to discuss
You have completed a cost / benefit analysis for prospective projects . You have a meeting with the project sponsor and portfolio manager to discuss which project select for the organization . Which of the following financial analysis methods and metrics would not help determine the best project to work on ? A Net present value ( NPV ) B Return on investment ( ROI ) Earned value management ( EVM ) D Internal rate of return ( IRR )