Question: You have completed estimating the durations for all tasks on your project and prepared the MS Project Plan shown in the attachment. Strangely, you notice

  1. You have completed estimating the durations for all tasks on your project and prepared the MS Project Plan shown in the attachment. Strangely, you notice that all your tasks take 5 days. Having struggled through PMAN 635 during your days as a UMUC student, you decide to use an optimistic time for each task of three days and a pessimistic time for each task of ten days. You feel that this will account for 90% of all the possible outcomes for each task. To save time, you export the tasks to the file Project problem 4 (attached) and use the Flash Fill feature to fill the column for m, the most likely times. Then you enter your optimistic and pessimistic times.

How much schedule reserve (days) should you add to your initial estimate in order to have a 90% chance of success?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!