Question: You have completed estimating the durations for all tasks on your project and prepared the MS Project Plan shown in the attachment. Strangely, you notice
- You have completed estimating the durations for all tasks on your project and prepared the MS Project Plan shown in the attachment. Strangely, you notice that all your tasks take 5 days. Having struggled through PMAN 635 during your days as a UMUC student, you decide to use an optimistic time for each task of three days and a pessimistic time for each task of ten days. You feel that this will account for 90% of all the possible outcomes for each task. To save time, you export the tasks to the file Project problem 4 (attached) and use the Flash Fill feature to fill the column for m, the most likely times. Then you enter your optimistic and pessimistic times.
How much schedule reserve (days) should you add to your initial estimate in order to have a 90% chance of success?