Question: You have completed your stakeholder analysis by identifying how each of your project stakeholders fits in a power - influence grid. Which of the following

You have completed your stakeholder analysis by identifying how each of your project stakeholders fits in a power-influence grid. Which of the following stakeholders should you prioritize when it comes to keeping them informed and helping them to accomplish their goals?
A high influence, high power stakeholder
A high influence, low power stakeholder
A low influence, low power stakeholder
A low influence, high power stakeholder