You have developed the following simple product structure of items needed for your gift bag for a
Fantastic news! We've Found the answer you've been seeking!
Question:
You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast attendees. You are expected to have the gift bags ready at PM However, you need to personalize the itemsmonogrammed pens, note pads, literature from the printer, etc. The lead time is hourto assemble Js once the other items are prepared. The other items will take a while as well. Given the volunteers you have, the other time estimates are item K hour item L hour and item M hours Develop a timephased assembly plan to prepare the gift bags.
LOADING...Click the icon to view the product structure.
Part
Choose the correct timephased assembly plan to prepare the gift bags.