Question: You have four projects: A, B, C,& D, with the following information. Which project would you select If your MARR IS 10% A B D
You have four projects: A, B, C,& D, with the following information. Which project would you select If your MARR IS 10% A B D PW $15 $12 $13 $16 IRR 12% 11% 16% 11% Select one: Do nothing alternative O A D B Not enough information You have four projects: A, B, C,& D, with the following information. Which project would you select If your MARR IS 10% A B D PW $15 $12 $13 $16 IRR 12% 11% 16% 11% Select one: Do nothing alternative O A D B Not enough information