Question: You have identified a risk event on your current project that could save $ 1 0 0 , 0 0 0 in project costs if
You have identified a risk event on your current project that could save $ in project costs if it occurs. Which
of the following is true based on this statement?
A This is a risk event that should be accepted because the rewards outweigh the threats to the project
B This risk event is an opportunity to the project and should be exploited
C This risk event should be mitigated to take advantage of the savings
D This is a risk event that should be avoided to take full advantage of the potential savings
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock