You have just taken over a project from another project manager. Incomplete information is available to you
Fantastic news! We've Found the answer you've been seeking!
Question:
You are assigned to manage a 12 month project estimated to cost $36,000 at the end of the project. Today is the end of month 3 and you are 20% complete. According to the finance Department you have spent $7500 to date.
Calculate the PV, EV, and the AC