Question: You have just used the network planning model and found the critical path length is 40 days and the variance of the critical path is

 You have just used the network planning model and found the

You have just used the network planning model and found the critical path length is 40 days and the variance of the critical path is 25 days. The probability that the project will be completed in 43 days or less is equal to (2 decimal accuracy) Multiple Choice O 0.70 O 0.78 0.55 0.60 0.73