Question: You have planned for a project to write a software application to take 1 year. The cost of the project is budgeted at $12,500 per

  1. You have planned for a project to write a software application to take 1 year. The cost of the project is budgeted at $12,500 per month. Give answers for both typical and atypical forecasts.

Six months into the project, you find that the software application is 50% complete and you have spent $70,000. Based on this information, fill in the following table.

Value

Budget at Completion

Planned Value

Earned Value

Actual Cost

Cost Variance

Schedule Variance

Cost Performance Index

Schedule Performance Index

Estimate at Completion

Estimate to Completion

Variance at Completion

  1. Is the project ahead of or behind schedule? How do you know?
  2. Is the project going to be completed over or under budget? How do you know?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!