Question: You have planned for a project to write a software application to take 1 year. The cost of the project is budgeted at $12,500 per
- You have planned for a project to write a software application to take 1 year. The cost of the project is budgeted at $12,500 per month. Give answers for both typical and atypical forecasts.
Six months into the project, you find that the software application is 50% complete and you have spent $70,000. Based on this information, fill in the following table.
|
| Value |
| Budget at Completion |
|
| Planned Value |
|
| Earned Value |
|
| Actual Cost |
|
| Cost Variance |
|
| Schedule Variance |
|
| Cost Performance Index |
|
| Schedule Performance Index |
|
| Estimate at Completion |
|
| Estimate to Completion |
|
| Variance at Completion |
|
- Is the project ahead of or behind schedule? How do you know?
- Is the project going to be completed over or under budget? How do you know?