Question: You have replaced the project manager on a project that is already in the execution phase. The project is behind the schedule and you have
You have replaced the project manager on a project that is already in the execution phase. The project is behind the schedule and you have been specifically brought in to ensure the project meets its schedule. You decide to review the network diagram created by the earlier project manager and you realize that the project is weeks behind the schedule. After reviewing the activities and the network diagram, you decide to crash the schedule. It means you
Add additional resources to the activities on the critical path
Discuss with the sponsors and explain how it is not going to be possible to meet the deadline
Decrease the scope of the project after discussing with the sponsors
Perform activities in parallel to decrease the schedule
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock