Question: You have sufficient resources to complete the project work within the deadline, but the resource histogram for the project is full of peaks and valleys.

You have sufficient resources to complete the project work within the deadline, but the resource histogram for the project is full of peaks and valleys. It looks like a rollercoaster. You must finish the project on the agreed upon finish date. A scheduling optimization technique that should be applied in this situation is called:

Resource optimization

Flattening the curve

Resource levelling

Resource smoothing