Question: You have three projects consisting of three sequential tasks each (design, followed by production, followed by training). You have one crew for each task. Schedule
You have three projects consisting of three sequential tasks each (design, followed by production, followed by training). You have one crew for each task. Schedule to minimize penalty. (Don't use critical chain)
Project | Design | Production | Training | Deadline | Penalty |
A | 4 weeks | 7 weeks | 3 weeks | Week 20 | $50K/week |
B | 3 weeks | 5 weeks | 1 week | Week 10 | $30K/week |
C | 1 week | 4 weeks | 1 week | Week 10 | $20K/week |