Question: You have three projects under consideration. Project A requires an investment of $10M and has an NPV of $2M. Project B requires an investment of

You have three projects under consideration. Project A requires an investment of $10M and has an NPV of $2M. Project B requires an investment of $5M and has an NPV of $2M. Project C requires an investment of $5M and has an NPV of $1.5M. Which project(s) should you take? A) Project A because it has the highest NPV. B) All of them as they are all positive NPV projects. C) None of the above.