Question: You hear a co - worker talking about somebody else's project. He only spent $ 2 0 0 0 to get $ 4 0

You hear a co-worker talking about somebody else's project. "He only spent $2000 to get $4000 worth of work done so far! Too bad he was supposed to have completed $5000 worth by now." What is your co-worker implying about the status of this project?
Question 5 options:
Ahead of Schedule and Over Budget
Behind Schedule and Under Budget
Ahead of Schedule and Under Budget
Behind Schedule and Over Budget