Question: You just learned that before the house can be cut in half, antique furniture must be removed from the house while the house material is
You just learned that before the house can be cut in half, antique furniture must be removed from the house while the house material is being studied and the weight of the house is calculated. You now have to create a work package to take care of this requirement. It is estimated that this work package will take days to complete. Update the schedule with this change by creating a work package under Move House" and connecting the new work package to the appropriate predecessors and successors.
Which of the following is true about the impact of this work package on the project?
Note: Before you proceed to the next question, close the file without saving changes, then reopen it to return to the original schedule.
Group of answer choices
There will be no impact on the timing of any other work package or the overall duration of the project
The project end date will be pushed days later than originally scheduled
Cut house in half" will be delayed by days, but the overall project will end as originally scheduled
Cut house in half" can be done as originally scheduled, but calculate house weight" will be delayed
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
