Question: You may need to use the appropriate technology to answer this question. Consider the PERT / CPM network with estimated times in weeks shown in
You may need to use the appropriate technology to answer this question.
Consider the PERTCPM network with estimated times in weeks shown in the following figure. The project is scheduled to begin on May
A project network with activities and directed arcs is shown.
Activity Start is connected to activity A
Activity A is connected to activity B and to activity C
Activity B is connected to activity D and to activity E
Activity C is connected to activity F and to activity G
Activity D is connected to activity F and to activity G
Activity E is connected to activity F
Activity F is connected to activity H
Activity G is connected to activity H
Activity H is connected to activity Finish.
Activity Finish has no arcs directed to other activities.
Activities AH have numeric values displayed under the Activity label. These values are given below:
A:
B:
C:
D:
E:
F:
G:
H:
The threetime estimate approach was used to calculate the expected times and the following table gives the variance for each activity.
Activity Variance
A
B
C
D
E
F
G
H
a
Give the expected project completion date and the critical path. Enter your critical path as a commaseparated list.
The expected project completion is
Incorrect: Your answer is incorrect.
weeks from May with a critical path of
Incorrect: Your answer is incorrect.
b
Based only on the critical path, by what date are you sure the project will be completed? Round your answer to one decimal place.
Incorrect: Your answer is incorrect.
weeks from May
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock