Question: You may need to use the appropriate technology to answer this question. Use the following network with activities and times estimated in days to answer
You may need to use the appropriate technology to answer this question.
Use the following network with activities and times estimated in days to answer the questions.
A project network with activities and directed arcs is shown.
Activity Start is connected to activity A to activity B and to activity C
Activity A is connected to activity D to activity E and to activity F
Activity B is connected to activity F
Activity C is connected to activity G and to activity H
Activity D is connected to activity K
Activity E is connected to activity I.
Activity F is connected to activity I.
Activity G is connected to activity I.
Activity H is connected to activity J
Activity I is connected to activity K
Activity J is connected to activity K
Activity K is connected to activity Finish.
Activity Finish has no arcs directed to other activities.
Activity Optimistic Most Probable Pessimistic
A
B
C
D
E
F
G
H
I
J
K
a
What are the critical path activities? Enter your answers as a commaseparated list.
Incorrect: Your answer is incorrect.
b
What is the expected time in days to complete the project?
Incorrect: Your answer is incorrect.
days
c
Based only on the critical path, what is the probability the project will take more than days to complete? Round your answer to four decimal places.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock