Question: You may need to use the appropriate technology to answer this question. To help with preparations, a couple has devised a project network to describe

You may need to use the appropriate technology to answer this question.
To help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date.
i)
The following table lists the activity time estimates (in weeks) for each activity.
\table[[Activity,Optimistic,Most Probable,Pessimistic],[A,4,5,6],[B,2.5,3,3.5],[C,7,8,9],[D,5,5.5,9],[E,5,7,9],[F,2,3,11],[G,7,9,15],[H,7,8,]]
(a) Within 21 weeks?
(b) Within 23 weeks?
(c) Within 27 weeks?
 You may need to use the appropriate technology to answer this

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!