You must procure a new network computer system for your company. You have a choice of two options. The two options are as follows:
Option 1 Option 2
Cost R30 000 R40 000
Installation Cost R10 000 R5 000
Yearly Maintenance R3 500 R3 000
Yearly Profit R10 000 R8 000
Project Lifetime 5 years 8 years
Estimated rate of return Year 0,1,2,3 = 10%, Year 4,5,6 = 8%, Year 7,8 = 5%.
For Option 1:
The NPV for year 0 is:
The NPV for year 1 is:
The NPV for year 2 is:
The NPV for year 3 is:
The NPV for year 4 is:
The NPV for year 5 is:
The NPV for option 1 is:
For Option 2:
The NPV for year 0 is:
The NPV for year 1 is:
The NPV for year 2 is:
The NPV for year 3 is:
The NPV for year 4 is:
The NPV for year 5 is:
The NPV for year 6 is:
The NPV for year 7 is:
The NPV for year 8 is:
The NPV for option 2 is:
Which is the better option to choose?
Step by Step Solution
There are 3 Steps involved in it
The detailed answer for the above question is provided below Answer To determine which option is better we need to calculate the Net Present Value NPV for both options and compare them Option 1 NPV in ... View full answer
Get step-by-step solutions from verified subject matter experts