Question: You received partial credit in the previous attempt. table [ [ TASK , SECONDS,TASKS THAT MUST ] , [ PRECEDE IT , , ]
You received partial credit in the previous attempt.
tableTASKSECONDS,TASKS THAT MUSTPRECEDE IT
The workday is hours long. The demand for the completed product is per day.
a Find the cycle time required to produce units per day.
Note: Round your answer to decimal place.
tableCycle time,seconds per unit
b What is the theoretical number of workstations?
Note: Round up your answer to the next whole number.
tableNumber of workstations,
d Balance the line using sequential restrictions and the longestoperatingtime rule. Note: Leave no cells blank be certain to enter wherever required. Round your answers to decimal place.
d Balance the line using sequential restrictions and the longestoperatingtime rule. Note: Leave no cells blank be certain to enter wherever required. Round your answers to decimal place.
tableWork Station,Task,Idle TimeIIIIIIIVV
e What is the efficiency of the line balanced as in part assuming it is running at the cycle time from part a
Note: Round your answer to decimal place.
Efficiency
f Suppose that demand rose from to units per day. What would you do
Note: Round your answer to the nearest whole number.
f Suppose that demand rose from to units per day. What would you do
Note: Round your answer to the nearest whole number.
cycle time to
seconds, which may require rebalancing the line.
g Suppose that demand rose from to units per day. What would you do
Note: Round your answer to decimal places.
Work overtime for
hours
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock