Question: You recently took over the assignment for a project. The project charter has been developed. What is an appropriate next step for you? A. Develop
You recently took over the assignment for a project. The project charter has been developed. What is an appropriate next step for you?
| A. | Develop the project milestone schedule. | |
| B. | Develop the risk register. | |
| C. | Get approval for the project management plan. | |
| D. | Develop project management plans |