Question: You status your time and materials project using EVM techniques and compile the following information in anticipation of a meeting with your client to discuss

 You status your time and materials project using EVM techniques and

compile the following information in anticipation of a meeting with your client

You status your time and materials project using EVM techniques and compile the following information in anticipation of a meeting with your client to discuss your progress: Initial price 2 $180,000 Total project duration = 6 months [assume 20 working days per month} Total direct cost budget = $90,000 You are 3 months into the project. Project % complete = 45% Actual cost [billing terms] = $90,000 Actual cost [direct] $40,000 Planned value (billing terms) = $101,250 Planned value (direct) = 550,000 Answer the following and show your work. 1. What is your identified Final Cost Forecast [in dollars}? 2. What is your identified Project duration Forecast {in days}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!