Question: You were presented with 5 methods to estimate your project time. If your project's main constraint is quality and you do not want to stress

You were presented with 5 methods to estimate your project time. If your project's main constraint is quality and you do not want to stress over time, which time estimating method is the best?
Question 5 options:
a. Parametric estimating
b. Reserve analysis
c. Three-point estimates
d. Analogous Estimating