Question: You will be evaluating three projects for Matthew Inc. Matthew's weighted average cost of capital or discount rate is 5%. The first project (A) will
You will be evaluating three projects for Matthew Inc. Matthew's weighted average cost of capital or discount rate is 5%.
The first project (A) will cost $50,000 initially. The project will then return cash flows of $10,000 for years 1 and 2, $20,000 in year 3, and $25,000 in year 4.
The second project (B) will cost $45,000 initially. The project will then return cash flows of $14,500 for four years.
The third project (C) will cost $50,000 initially. The project will then return cash flows of $18,000 for three years.
Question 1 (0.5 points)
What is Project A's NPV?
Question 2 (0.5 points)
What is Project A's IRR?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
