Question: You work as a project manager for uCertify Inc. You have to enable roll-ups of both resource assignments and availability data to a higher level.
You work as a project manager for uCertify Inc. You have to enable roll-ups of both resource assignments and availability data to a higher level. Which of the following diagrams will you use to achieve the task? A Work breakdown structure B O Resource breakdown structure C Roles and responsibility matrix D O Project network diagram