Question: Your Agile project team is using Scrum to manage the work and deliverables for your project. Which of the below is not one of the

Your Agile project team is using Scrum to manage the work and deliverables for your project. Which of the below is not one of the Scrum events or artefacts?

Your Agile project team is using Scrum to manage
Product Backlog, where the product owner manages a prioritized list of planned product items which evolves from sprint to sprint. Sprint Backlog, which are the items selected in Sprint Planning for the upcoming sprint. Increments, or Features, which are all the Product Backlog items completed during a Sprint and a step toward the main vision