Question: Your boss would like to suggest changes that could be made to the project that would significantly shorten it. What would you suggest? exhibit 10.14
exhibit 10.14 Work Breakdown Structure and Activities for the Cell Phone Design Project MAJOR PROJECT TASKS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION Product specifications (P) Overall product specifications Hardware specifications Software specifications Market research P2, P3 y Supplier specifications (s) Hardware Software Market research Excel: Cell_Phone Design SI, D7 S1 Product design (D) Circuits Battery Display Outer cover User interface Camera Functionality 9889999 S1, S2, S3 D5, D6 = Product integration (1) Hardware Software Prototype testing Subcontracting (M) Vendor selection Contract negotiation D1, D2, D3, D4, D6 D7 11,12 ss D7 13,1