Question: Your company is considering two mutually exclusive projects, Project A and Project B. The cash flows from the projects are summarized below Yeal 0 $25000
Your company is considering two mutually exclusive projects, Project A and Project B. The cash flows from the projects are summarized below Yeal 0 $25000 $30,000 $45.000 $50.,000 $60,000 $100,000 2 3 5 The firm has finally determined that the cost (T-o cash flow) of Project B is $144,000. Based on this information, determine the discount rate at which the NPV for both projects is the same. 14.03% 15.57% 13.30% 14.79% 12.59%