Question: Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown here: The projects are not equally risky,
| Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown here: | |||||
| The projects are not equally risky, and their cost of capital is 12% and 14%% respectively. | |||||
| Year | Project X CF | Project Y CF | |||
| 0 | -5000 | -5000 | |||
| 1 | 1000 | 4500 | |||
| 2 | 1500 | 1500 | |||
| 3 | 2000 | 1000 | |||
| 4 | 4000 | 500 | |||
| 5 | 500 | ||||
| Cost of capital | 12% | 14% | |||
| a. Which project has the higher NPV? | |||||
| b. Which project has the shortest discounted payback? | |||||
| c. Which project has the higher MIRR? Which project should be chosen based on the indicators you've calculated?
| |||||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
