Question: Your compary was awarded a culvert contract. The contract manager has appointed you to manage the project and has requested you to provide a schedulo

Your compary was awarded a culvert contract. The contract manager has appointed you to manage the project and has requested you to provide a schedulo for the chent The contract manager handad you the table below, showing a breakdown of activities involved, together with their duration. The Start date is the 01/02/2024(1st February 2021).
Table 1: Activity Breakdown
\table[[,Task Name,Duration,Predecessor,Resource name],[1,Setting out Excavation,1 day,,Surveyor],[2,Eartwworks/Ste Clearing,1 day,1,Excavator + General latous],[3,Bulk Excavation,3 days,1+2,Excavalor],[4,Compacton of Culvert bases 2,2 dives,3,Compactor + General Labout],[5,Setting out Binding,1 day,4,Surveyor],[6,Blinding (base 1-8),2 days,5,Concrete Foteman + General Labou],[7,Steel Fiong (base 1-8),3 days,655,Sleel Fixer + Reinforcement (4,61)
Your compary was awarded a culvert contract. The

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!