Question: Your construction project requires site security. Considering that the day shift is activity A and the night shift is activity B, what type of dependency

Your construction project requires site security. Considering that the day shift is activity A and the night shift is activity B, what type of dependency would you include between activity B and activity A? Question 17 options: FS - Finish to Start SF - Start to Finish FF - Finish to Finish SS - Start to Start