Question: Your construction project was damaged by an earthquake. Your contractor says that he cannot fulfill the terms of the contract due to a specific clause

Your construction project was damaged by an earthquake. Your contractor says that he cannot fulfill the terms of the contract due to a specific clause you both had signed the contract. He is referring to the: Force majeure clause Fixed price clause Contract obligation terms None of the above