Question: Your current project can be summarized as: EV = 750,000 AC = 600,000 PV = 500,000 What is your project's SPI? -3.0 -1.5 1.5 3.0
Your current project can be summarized as: EV = 750,000 AC = 600,000 PV = 500,000 What is your project's SPI? -3.0 -1.5 1.5 3.0