Question: Your division is considering two projects. Its WACC is 1 2 % , and the projects' after - tax cash flows ( in millions of
Your division is considering two projects. Its WACC is and the projects' aftertax cash flows in millions
of dollars would be as follows:
a Calculate the projects' NPVs and Cummulative Cash Flow
b Which project would you choose?
Project
Time period:
Cash flow:
Cumulative cash flow:
Payback only enter the year
Project
Time period:
Cash flow:
Cumulative cash flow:
Payback
only enter the year