Question: Your firm is considering a project which will cost $21 million after-tax today and is expected to generate after-tax cash flows of $9 million per
Your firm is considering a project which will cost $21 million after-tax today and is expected to generate after-tax cash flows of $9 million per year at the end of the next 4 years. If the company waits for 2 years, the project will cost $25 million after-tax and there is a 90% chance that the project will generate $12 million per year for four years and a 10% chance that the project will generate $8 million per year for 4 years, Assume all cash flows are discounted at 12%. Estimate the value of the timing option. $1.29 million O $1.68 million O $1.74 million $1.88 million O $1.82 million
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts