Question: Your options for shipping $ 1 0 4 , 3 1 0 of machine parts from Baitimore to Kuala Lumpur, Malaysia, are ( 1 )

Your options for shipping $104,310 of machine parts from Baitimore to Kuala Lumpur, Malaysia, are (1) use a ship that will take 30 days at a cost of $3,630, or (2) truck the parts to Los Angeles and then ship at a total cost of $5,040. The second option will take only 22 days. You are paid via a letter of credit the day the parts arrive. Your holding cost is estimated at 30% of the value per year.
If you have a third option and it costs only $4,020 and also takes 22 days, what is your most economical plan?
The daily holding cost of Alternative 1 is $ (Enler your response rounded to two decimal places)
The daily cost of fasler shipping with Alternative 2 is $.(Eriter your response rounded to two decimal places.)
The daily cost of faster shipping with Alternative 3 is .(Enter your response rounded to two decimal places.) is more economical.
 Your options for shipping $104,310 of machine parts from Baitimore to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!