Question: Your organization is evaluating a project to decide whether to go or not go for it. The estimated cost of this project is 500,000 USD

Your organization is evaluating a project to decide whether to go or not go for it. The estimated cost of this project is 500,000 USD and duration of this project is 3 years. At the end of the first year, you will get 200,000 USD revenue. At the end of the second year, you will get 170,000 USD. At the end of the third year, you will get 200,000 USD. Considering the 8% discount rate, calculate NPV and comment on this project.

Please show workings