Question: Your production process has four steps: Step 1 - one worker Drier for the plastics capacity 5000 lbs/hr 1 flamingo = 5.0 lbs Step 2
| Your production process has four steps: | |||||
| Step 1 - one worker | Drier for the plastics | capacity 5000 lbs/hr | 1 flamingo = 5.0 lbs | ||
| Step 2 - two workers | Molding machine | capacity 50 10 packs per hour | |||
| Step 3 - three workers | Visual inspection and finishing touches | 6 sec per flamingo per worker | |||
| Step 4 - two workers | packing in boxes of 10; attaching labels | 1 minute per box per worker | |||
| Output in units (10-packs) per hour | Processing time (sec) (10-pack) | Takt Time (sec) (10 pack) | Slack (sec) | Time Idle (%) | |
| S1 | |||||
| S2 | |||||
| S3 | |||||
| S4 | |||||
| Q8. | There seems to be a lot of waste and idle time at the plant. How many workers can you let go at station 3 | ||||
| a. | none | ||||
| b. | one | ||||
| c. | two | ||||
| d. | you need to add a worker | ||||
| Output in units (10-packs) per hour | Processing time (sec) (10-pack) | Takt Time (sec) (10 pack) | Slack (sec) | Time Idle (%) | |
| S1 | |||||
| S2 | |||||
| S3 | |||||
| S4 | |||||
| Q9. | You decide to let go all the redundant workers, in both shifts. What are the total savings ? | ||||
| Remember: your average worker costs you US$ 50,000 a year | |||||
| a. | $ 200,000 | per year | |||
| b. | $ 300,000 | per year | |||
| c. | $ 150,000 | per year | |||
| d. | $ 100,000 | per year | |||
| You would like your plant to run like a well-oiled machine but a month after investing US$ 600,000 dollars to replace machinery and hire a new supply chian manager - upon visiting the factory you see some workers working non-stop and others walking around chatting and laughing. Now that you are a business owner, you think this is not a good sign ... so you look into it. | ||||
| First you establish the plant's takt time - the max time available to produce a unit (10 pack) and meet demand (now 200,000 units). You have 2 shifts of 8 hours each 5 days a week for 50 weeks a year | ||||
| total seconds = 2 machines 2 shifts 8 hours 5 days a week 50 weeks a year | ||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock