Question: Your project champion has asked you to include a PERT chart in the appendix of your project charter. You are up to the task and

Your project champion has asked you to include a PERT chart in the appendix of your project charter.
You are up to the task and know that PERT stands for:
Select one:
program evaluation and review technique
project effectiveness and requirements template
people, equipment, requirements, and technology
project estimating and requirements terminology