Question: Your project has a tight deadline, and planning needs to start immediately; otherwise, there may be risks of delays. The sponsor has not signed the

Your project has a tight deadline, and planning needs to start immediately; otherwise, there may be risks of delays. The sponsor has not signed the project charter and will not be available for another two weeks. What should you do