Question: Your project has an initial critical path that is 128 days long. The next longest path is 122 days long. If you reduce the initial
- Your project has an initial critical path that is 128 days long. The next longest path is 122 days long. If you reduce the initial critical path by 10 days, the entire projects duration with decrease by 10 days (1).
- True
- False