Question: Your project has been under way for about 2 months of a total 1 8 - month timeline. At lunch one day, a colleague mentions
Your project has been under way for about months of a total month timeline. At lunch one day, a colleague mentions that Ranga, a lead operations manager, has complained to a few people that they aren't sure what's going on with the project, and it could be way off track. You take note of this comment because it indicates that you need to improve which aspect of the Project Work Performance Domain?
A Developing and managing the team
B Engaging stakeholders and keeping them informed about project issues and risks
C Directing and managing project work quality
D Comparing actual progress against approved baselines