Question: Your project has four activities. Below is the current status of each activity. Activity A was supposed to cost $350,000 when complete. Its costs so

Your project has four activities. Below is the current status of each activity.

Activity A was supposed to cost $350,000 when complete. Its costs so far are $265,000. It is 45% complete. The activity has completed 7 weeks of a planned 15-week schedule.

Activity B is at the end of week 2 of a planned 4-week effort. It is 75% complete. It was to cost $190,000 when finished. Its costs to date are $150,000.

Activity C is finished. It finished 2 weeks late. It cost $200,000 and it was planned to cost $250,000.

Activity D is at the end of its fourth of a planned 6-week schedule. It has cost $350,000 so far. It was estimated to cost $500,000 when finished. It is approximately 55% complete.

Using these data, calculate the following.

1.Calculate the CV, SV, CPI, and SPI for each activity and the total project.

2.What is your assessment of the project at this time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!