Question: Your project is already delayed by some rework and changes. As a project manager, you have identified that availability of certain key resource is now

Your project is already delayed by some rework and changes. As a project manager, you have identified that availability of certain key resource is now limited or constrained, Your top priority for allocating that resource in your revised schedule should aim for: Training project team for rework mitigation 11. 111. IV. Fast-tracking non-critical activities with alternate resources Attending critical activities and managing with float