Question: Your project is behind schedule when _ _ _ _ _ is less than _ _ _ _ _ . Select an answer: planned value;

Your project is behind schedule when _____ is less than _____.
Select an answer:
planned value; earned value
actual value; planned value
earned value; planned value
earned value; actual value