Question: Your project is divided into five major subprojects. Subproject P involves developing specifications for the new cell phone. Here, decisions related to such
Your project is divided into five major subprojects. Subproject involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject supplier specifications. These involve engineering details for how the product will perform.
The individual components that make up the product are the focus of subproject D Subproject brings all the components together, and a working prototype is built and tested.
Finally, in subproject V suppliers are selected and contracts are negotiated.
Draw a project network that includes all the activities.
Calculate the start and finish times for each activity and determine the minimum number of weeks for completing the project. Find the activities that are on the critical path for completing the project in the shortest time.
Identify slack in the activities not on the project critical path.
You have been asked to study the impact of making two changes to how the project is organized. The first change involves using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject product specifications the team would work on and all in parallel. In other words, there would be no precedence relationships within a subprojectall tasks within a subproject would be worked on at the same time and each would take the same amount of time as originally specifled. With this new design, all the subprojects would be done sequentially with done first, then S D I, and finally V What would be the expected impact on how long it would take to complete the project if this change were made?
The second change to consider would be to select the suppliers during subproject and have them work directly with the dedicated teams as described in step This would involve adding an additional activity to subproject called supplier selection and contract negotiation P with a duration of weeks. This new activity would be done in parallel with PI P P and P Subprojects S and V would be eliminated from the project. What would be the expected impact on how long it would take to complete the project if this additional change were made?
Evaluate the impact of making these changes using criteria other than just the time to complete the project. Do you think it would be best to try to make these changes in how the firm runs this and future cell phone design projects?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock