Question: Your project is tasked with re - paving 5 0 miles of road You plan calls for you to pave 2 miles per month at

Your project is tasked with re-paving 50 miles of road You plan calls for you to pave 2 miles per month at a cost of $50,000 per mile. The first month your periodic EV is $50,000 and your periodic Actual Cost is $150,000. The second month your periodic EV $150,000 and your periodic Actual Cost is $110,000. After the 3 rd month you have 42 miles remaining to pave and you have a cumulative Actual Cost of $350,000.
Determine the periodic values for Month 3 for each of the terms
\table[[Term,Value ($)],[Budget At Completion, miles * $50,000
 Your project is tasked with re-paving 50 miles of road You